Blew out a control joint on a 40 foot driveway in Mesa and had to fix it before the homeowner got home
Was finishing a 40 foot driveway pour in Mesa back in March and my cut guy showed up about 90 minutes late with the saw. By the time he got there the slab was already past the window and when he finally hit the control joint it spider cracked about 3 feet off the line. I had him keep cutting and I grabbed a bucket of stiff mix and a margin trowel, packed the crack tight, then floated it back in while the whole thing was still green enough to blend. We covered it with curing blankets and I told the homeowner we were keeping it wet for a day longer, which was true, and the crack never opened back up. Three months later you can't find it unless you know where to look. What are you all doing when the saw shows up late and the pour is already setting up on you?