Can we talk about the 45 minute concrete truck window?
I was reading the NRMCA spec sheet last week and saw that once a truck leaves the plant you really only have about 90 minutes total before the mix starts setting up, and that clock includes the drive. Our batch plant is 25 minutes from the Riverside job, so that leaves a pretty tight window to get placed and finished. I had been treating the discharge time as the whole clock and it turns out the drum time counts against you too. How are you all planning pour schedules around drive time, do you just over-order trucks and eat the short loads or do you build in a buffer plant closer to the site?