The staging guy in Houston saved us from a 2 hour crane delay with a chalk line
We had a crane pick scheduled for 6am at the Hollister site in Houston and the rigging crew got there at 4:45 only to find the mats we planned to set the outriggers on were buried under a pile of rebar that got delivered late the day before. Nobody had logged the rebar drop so it sat right in our lift zone. The staging lead walked the whole pad with a chalk line before anyone showed up, marked it out, and we had the mats reset by 5:30. Now I'm wondering how many other sites skip the pre-lift walk because the schedule says the pad is clear, has anyone built a checklist for this?
Does a chalk line really take the place of a full walk though? It marks the pad, sure, but whoever marks it still has to see the rebar first, and on a lot of jobs the guy with the chalk doesn't roll up till 6. Our super started doing a ten minute pad check at the end of the day before, with the lift zone taped off so nothing gets dropped in it overnight no matter what the schedule says. The walk the morning of is good but catching it the day before is what kept that rebar from landing there in the first place.