Unpopular opinion: hitting 92% on-time concrete pours is not the flex my boss thinks it is
We just closed out March at 92% on-time pour rate across 14 site deliveries in Phoenix, and my PM printed the number on a banner like we won something. That 8% miss is 9 pours that got pushed, and each one meant a crew standing around or a pump truck sitting idle at $400 an hour. Two of those misses came from one batch plant change I flagged back in January that nobody wanted to hear about. So who is really eating those 9 late loads, because it sure isn't the banner?